Towards a February Opening

By King & Godfree Monday November 6, 2017 See More —

The biggest news this month is that we’ve completed all the major steel construction work for the rooftop bar which means we can not only finish the flooring work for the bar but that the whole building is now completely watertight. The fitout on the ground floor – all the plaster, studwork and services – is now underway, moving us a step closer to a January handover and a February opening.

Waterproofing work for basement bar is now also complete and the windows have been fully installed on both the ground and upper floors.

We’ve also started recruiting for positions throughout the business and so combined with the construction work moving towards completion are feeling excited that the re-opening of the new King & Godfree is getting so close.

Stay tuned for further developments.